Question: 4.1 Using the tasks in Table 2, construct a Work Breakdown Structure (WBS) for the e-filing project. (10) 4.2 From your WBS, construct a Gantt

4.1 Using the tasks in Table 2, construct a Work Breakdown Structure (WBS) for the e-filing project. (10)
4.2 From your WBS, construct a Gantt Chart for the e-filing project. (10)
Duration(weeks) 2 4 3 Question 4 [20] Table 2: WBS activities in the e-filing project Number Description of task A Interview staff and make a list of requirements. B Assess alternatives and choose the most appropriate Specify and order new soft and hardware as required. D Test and install the new hardware and software. Test the package to assess suitability. F Draw up a training plan for staff. Train staff on the new programme. H Make a follow-up and do acceptance test. 1 Load data and implement the new system. 2 D E 1 1 G 3 3 1Step by Step Solution