Question: 3. Given the project network and baseline information below, complete the form to develop a status report for the project at the end of period


3. Given the project network and baseline information below, complete the form to develop a status report for the project at the end of period 4 and the end of period 8 . From the data you have collected and computed for periods 4 and 8 , what information are you prepared to tell the customer about the status of the project at the end of period 8 ? End of Period 4 Task A B C D E Cumulative Totals Actual \% Complete Finished 50% 33% 0% 0% EVAC300220015003003000PV400240015000 Actual \% Complete Finished Finished Finished 25% 33% 0% \begin{tabular}{l} sv \\ \\ \\ - \\ \hline \end{tabular} End of Period 8 Task A B C D E F Cumulative Totals
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
