Question: 3 Given the table below: Activity Duration (weeks) Dependency A 5 B 4 A C 12 A D 7 A E 9 B F 10

3 Given the table below: Activity Duration (weeks) Dependency A 5 B 4 A C 12 A D 7 A E 9 B F 10 B, C G 1 C, D H 13 A, E I 7 E, F, G J 4 H, I K 7 I L 8 J, K, G M 3 L N 12 H, M O 12 N P 5 O A. Draw a project network from the table above 1) What activity(s) is a burst activity? 2) What activity(s) is a merge activity? 3) What is the length of the project? 4) What is the critical path? B. Draw the Gantt char