Question: Consider the project describe in the table below Activity Duration Immidiate Predesessor A 5 - B 7 A C 4 A D 3 B E

Consider the project describe in the table below Activity Duration Immidiate Predesessor A 5 - B 7 A C 4 A D 3 B E 5 B, C F 1 D, E What are the Earliest Start Times (EST) and Early Finish Times (EFT) for activity D? A) 9 and 15 B) 9 and 12 C) 12 and 15 D) 12 and 14