Question: Consider the project described in the table below: Activity Duration Immidiate Predecessor A 5 B 7 A C 4 A D 5 B E 9

Consider the project described in the table

Consider the project described in the table below: Activity Duration Immidiate Predecessor A 5 B 7 A C 4 A D 5 B E 9 B F 5 C.D G 1 E,F What is the earliest start time (EST) and latest start time (LST) of activity C? O EST = 5 and LST = 5 EST = 5 and LST = 13 O EST = 5 and LST = 16 O EST = 5 and LST = 12