Question: 3 . Insert activity 3 into Figures 9 . 2 , 9 . 3 , and 9 . 4 , which is restrained by activity

3. Insert activity 3 into Figures 9.2,9.3, and 9.4, which is restrained by activity 1 and has a finish to finish relationship with activity 2. The duration of the three is 12 days. (A) What is the critical path of activities? (B) Which activities have float? (C) What is the new EF date of this string of activities?