Question: Using the information below, a task that is on the critical path for this project has increased by 7 days. Will the project end date

Using the information below, a task that is on the critical path for this project has increased by 7 days. Will the project end date be delayed? If so, by how much? Please show your work.

3 critical paths

Path 1: A,B,E,H,K, L;

Path 2: A,C,F,I,K,L;

Path 3: A,D,G,J,K,L

Activity Description Predecessor Duration Early Start Early Finish Late Start Late Finish Total Slack Free Slack
A Systems Design None 2 0 2 0 2 0 0
B Subsystem A Design A 1 2 3 2 3 0 0
C Subsystem B Design A 1 2 3 2 3 0 0
D Subsystem C Design A 1 2 3 2 3 0 0
E Program A B 2 3 5 3 5 0 0
F Program B C 2 3 5 3 5 0 0
G Program C D 2 3 5 3 5 0 0
H Subsystem A Test E 1 5 6 5 6 0 0
I Subsystem A Test F 1 5 6 5 6 0 0
J Subsystem A Test G 1 5 6 5 6 0 0
K Integration H,I,J 3 6 9 6 9 0 0
L Integration Test K 1 9 10 9 10 0 0

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!