Question: Using the information below, a task that is on the critical path for this project has increased by 7 days. Will the project end date
Using the information below, a task that is on the critical path for this project has increased by 7 days. Will the project end date be delayed? If so, by how much? Please show your work.
3 critical paths
Path 1: A,B,E,H,K, L;
Path 2: A,C,F,I,K,L;
Path 3: A,D,G,J,K,L
| Activity | Description | Predecessor | Duration | Early Start | Early Finish | Late Start | Late Finish | Total Slack | Free Slack | |||
| A | Systems Design | None | 2 | 0 | 2 | 0 | 2 | 0 | 0 | |||
| B | Subsystem A Design | A | 1 | 2 | 3 | 2 | 3 | 0 | 0 | |||
| C | Subsystem B Design | A | 1 | 2 | 3 | 2 | 3 | 0 | 0 | |||
| D | Subsystem C Design | A | 1 | 2 | 3 | 2 | 3 | 0 | 0 | |||
| E | Program A | B | 2 | 3 | 5 | 3 | 5 | 0 | 0 | |||
| F | Program B | C | 2 | 3 | 5 | 3 | 5 | 0 | 0 | |||
| G | Program C | D | 2 | 3 | 5 | 3 | 5 | 0 | 0 | |||
| H | Subsystem A Test | E | 1 | 5 | 6 | 5 | 6 | 0 | 0 | |||
| I | Subsystem A Test | F | 1 | 5 | 6 | 5 | 6 | 0 | 0 | |||
| J | Subsystem A Test | G | 1 | 5 | 6 | 5 | 6 | 0 | 0 | |||
| K | Integration | H,I,J | 3 | 6 | 9 | 6 | 9 | 0 | 0 | |||
| L | Integration Test | K | 1 | 9 | 10 | 9 | 10 | 0 | 0 | |||
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts