Question: The information about a project with 10 activities is shown below. Activity A, 9 days, IP = none Activity B, 19 days, IP = none

The information about a project with 10
The information about a project with 10 activities is shown below. Activity A, 9 days, IP = none Activity B, 19 days, IP = none Activity C, 23 days, IP = A Activity D, 22 days, IP =A, B Activity E, 17 days, IP = B Activity F 16 days, IP = 0 Activity G: 36 days, IP =D Activity H, 19 days, IP = E Activity K 6 days, IP = F G Activity M 23 days; IP = GH The slack of activity F is days