Question: 3. The table below shows the ready time, process time and due date of 7 jobs. Job ID Ready Time Process Time Due Date 1

3. The table below shows the ready time, process
3. The table below shows the ready time, process time and due date of 7 jobs. Job ID Ready Time Process Time Due Date 1 12 2 17 2 1 4 20 3 5 14 3 18 5 3 2.1 9 13 7 3 0 23 Find a sequence to minimize total tardiness as much as possible (preferably below 21). Drw your sequemce on a Gantt Chart liko time-line