Question: operation design 3. The table below shows the ready time, process time and due date of 7 jobs. Process Time 2 4 Job ID Ready

operation design
operation design 3. The table below shows the
3. The table below shows the ready time, process time and due date of 7 jobs. Process Time 2 4 Job ID Ready Time 12 2 1 3 3 4 0 5 5 6 9 7 7 Due Date 17 20 14 18 24 13 23 3 3 6 3 Find a sequence to minimize total tardiness as much as possible (preferably below 21). Draw your sequence on a Gantt Chart like time-line