Question: 3. The table below shows the ready time, process time and due date of 7 jobs. Job ID Process Time Due Date 2 3 Ready

3. The table below shows the ready time, process

3. The table below shows the ready time, process time and due date of 7 jobs. Job ID Process Time Due Date 2 3 Ready Time 12 1 3 0 18. 6 9 7 Find a sequence to minimize total tardiness as much as possible (preferably below 21). Draw your sequence on a Gantt-Chart like time-line