Question: 3. The table below shows the ready time, process time and due date of 7 jobs. Job ID Ready Time Process Time Due Date 1

3. The table below shows the ready time, process

3. The table below shows the ready time, process time and due date of 7 jobs. Job ID Ready Time Process Time Due Date 1 12 2 17 2 1 4 20 3 3 5 14 4 0 3 5 5 3 24 6 9 6 7 7 3 23 18 13 Find a sequence to minimize total tardiness as much as possible (preferably below 21). Draw your sequence on a Gantt-Chart like time-line

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!