Question: 3) Use the values below in the table to undertake the following: a) Calculate the activity durations. b) Draw the network diagramme. c) Which path

3) Use the values below in the table to undertake the following: a) Calculate the activity durations. b) Draw the network diagramme. c) Which path is critical? Please, justify your response. d) How closely should the other path be watched and why? Activity A B D E F Predecessor Optimistic 4 A 2 A 6 B 3 7 DE 7 Likely 6 5 7 9 9 11 Pessimistic 10 8 9 20 11 19 4) Construct a network using the information in the table and identify the critical path. Predecessor Activity B D E F G H Time 4 6 9 11 16 4 8 7 A A B B, C D E, F G
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
