Question: 30 points Q4) Apply Critical Path method over the following network diagram, identify critical activities and calculate total project duration. Also calculate the following for

30 points Q4) Apply Critical Path method over the

30 points Q4) Apply Critical Path method over the following network diagram, identify critical activities and calculate total project duration. Also calculate the following for each activity; a) Early start (ES) & Early Finish (EF) b) Late Start (LS) & Late Finish (LF) c) Total Float & Free Float Activities A B A B Durations (Months) 2 3 6 1 6 3 4 BEGIN D D E END E F G F G (CLO-2, Marks: 30)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!