Question 31 > This Test: 39 pt B 1 D 7 2 E 3 3 6 Activity Time 2 Earliest Finish Activity A Slack Earliest Start 0 2 2 Latest Finish 2 0 Latest Start 0 3 2. B 3 4 1 1 3 5 0 D 5 10 7 3 4 11 E 3 5 8 11 3 F 5 11 5 11 0 G 4 11 15 11 15 0 Bi A Deskto Act T Activity . B D E FI G 4 Using the information shown in the table above, what is the activity time for activity F? O A. 6 OB. 1 O C. 5 OD. 11 Type here to search