Question: 3.3: Construct the Network Diagram for the Project listed below and identify the critical path and most risky activity. (4 Marks) Activity Predecessor Duration (days)

3.3: Construct the Network Diagram for the

3.3: Construct the Network Diagram for the Project listed below and identify the critical path and most risky activity. (4 Marks) Activity Predecessor Duration (days) A 7 B A 5 C A 3 D B 6 E C 3 F 4 G DE 8 H F G 9