Question: 38 When scheduling project tasks, which type of task dependency refers to should have, not the must have Group of answer choices Internal dependency Mandatory
38
When scheduling project tasks, which type of task dependency refers to "should have", not the "must have"
Group of answer choices
Internal dependency
Mandatory dependency
External dependency
Discretional dependency