Question: -4 a Given the activity time estimates below, what is the expected time for Activity A? (round to 2 decimals as needed) Activity Optimistic Time

-4 a Given the activity time estimates below,
-4 a Given the activity time estimates below, what is the expected time for Activity A? (round to 2 decimals as needed) Activity Optimistic Time Most Likely Time Pessimistic Time A 2.2 6.0 6.8 ut of 2.1 3.9 3.9 B C 1.1 1.9 5.9 6.1 6.9 8.1 Select one: O a. 5.00 O b. 2.50 O c. 2.43 O d. 5.50 Oe. None of the other options. Of. 3.60 Og. 4.85 Oh. 6.97