Question: Given the activity time estimates below, what is the expected time for Activity A? (round to 2 decimals as needed) Activity Optimistic Time Most Likely

Given the activity time estimates below, what is the expected time for Activity A? (round to 2 decimals as needed)

Activity

Optimistic Time

Most Likely Time

Pessimistic Time

A

1.9

6.0

7.2

B

1.9

4.1

4.1

C

0.9

2.2

6.1

D

5.9

7.1

8.0

Select one:

a. 4.60

b. 7.05

c. 5.03

d. 2.52

e. None of the other options.

f. 3.73

g. 5.52

h. 2.63