Question: Given the activity time estimates below, what is the expected time for Activity D? (round to 2 decimals as needed) Activity Optimistic Time Most Likely

Given the activity time estimates below, what is the expected time for Activity D? (round to 2 decimals as needed)

Activity

Optimistic Time

Most Likely Time

Pessimistic Time

A

1.9

6.1

7.0

B

1.8

3.8

3.8

C

1.1

2.0

6.0

D

6.0

6.9

8.2

Select one:

A. None of the other options.

B. 3.47

C. 5.10

D. 6.97

E. 2.52

F. 3.52

G. 5.55

H. 7.03