Question: Given the activity time estimates below, what is the expected time for Activity D? (round to 2 decimals as needed) Activity Optimistic Time Most Likely
Given the activity time estimates below, what is the expected time for Activity D? (round to 2 decimals as needed)
| Activity | Optimistic Time | Most Likely Time | Pessimistic Time |
| A | 1.9 | 6.1 | 7.0 |
| B | 1.8 | 3.8 | 3.8 |
| C | 1.1 | 2.0 | 6.0 |
| D | 6.0 | 6.9 | 8.2 |
Select one:
A. None of the other options.
B. 3.47
C. 5.10
D. 6.97
E. 2.52
F. 3.52
G. 5.55
H. 7.03