Question: Given the activity time estimates below, what is the expected time for Activity A? (round to 2 decimals as needed) Activity Optimistic Time Most Likely

Given the activity time estimates below, what is
Given the activity time estimates below, what is the expected time for Activity A? (round to 2 decimals as needed) Activity Optimistic Time Most Likely Time Pessimistic Time 1.9 6.0 7.2 B 2.2 4.2 4.2 C 0.9 2.1 5.8 D 6.0 7.1 7.9 Select one: O a. 4.60 Ob. None of the other options. O c. 3.87 O d. 5.52 Oe. 7.05 O 1.2.52 Og. 2.52 Oh.5.03