Question: 4) Activity Predecessor(s) Optimistic Most likely Pessimistic A none 4 8 10 B A 2 8 24 C A 8 12 16 D A 4
4)
Activity Predecessor(s) Optimistic Most likely Pessimistic
A none 4 8 10
B A 2 8 24
C A 8 12 16
D A 4 6 10
E B 1 2 3
F E, C 6 8 20
G E, C 2 3 4
H F 2 2 2
I F 6 6 6
J D,G,H 4 6 12
K I, J 2 2 3
- What is the expected time for activity C?
- What is the variance for activity C?
- Based on your calculation of expected times, what is the critical path?
- What is the estimated time of the critical path?
- What is the activity variance along the critical path?
- What is the probability of completion of the project before week 36?