Question: 4. Below are the data for a Time-Cost CPM Scheduling analysis. The time is in days and the costs include both direct and indirect costs.

 4. Below are the data for a Time-Cost CPM Scheduling analysis.

4. Below are the data for a Time-Cost CPM Scheduling analysis. The time is in days and the costs include both direct and indirect costs. (10 marks) Immediate Normal Crash Normal Crash Activity Predecessor Time Cost $200 $300 $300 $500 $500 Cost $400 $%600 $300 $550 $900 Time None B and C If you crash this project to reduce the total time by four days, what is the total time of the project and total cost