Question: 4. Given the following highway rerouting project: Immediate Predecessor Activity Activity Time (months) 6 A B D E F G 5 2 B 6 C,B

4. Given the following highway rerouting project:
4. Given the following highway rerouting project: Immediate Predecessor Activity Activity Time (months) 6 A B D E F G 5 2 B 6 C,B 3 C,B 3 DE 5 (a) Draw the network. (b) Find the ESTs, LSTS, EOTS, LOTs, and slacks. (c) Find the critical path. (d) If the project has a 1 1/2 year deadline for re- opening, should we consider crashing some activities? Explain