Question: Subject: Quantitative Analysis for Business Operations 2. Given the following network project : Activity Estimated time (mos.) Immediate predecessor A 10 - B 12 -
Subject: Quantitative Analysis for Business Operations
| 2. Given the following network project: | ||
| Activity | Estimated time (mos.) | Immediate predecessor |
| A | 10 | - |
| B | 12 | - |
| C | 15 | - |
| D | 18 | A |
| E | 7 | C |
| F | 9 | B, C |
| a. Develop a network diagram. | ||
| b. How long will it take to complete the project? | ||
| c. Which activities are on the critical path? | ||
| d. How much stack is in each activity? | ||
| e. What is the impact on the critical time if the time for Activity A is increased to 14 months? | ||
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock