Question: 41. For the above project network (times is given in weeks), if EF for activity C is week 4 and EF for activity F is

41. For the above project network (times is given in weeks), if EF for activity C is week 4 and EF for activity F is week 11
True
False
42.For the above project network, if LS for activity G is week 16, LS for activity F is week 9
True
False
QUESTION 43
43.For the above project network if LS for activity E is week 9, LS for activity D is week 4
True
False
QUESTION 44
44. If LF=9 and LS=5 for activity C, we can say its slack is 4 and is a non-critical activity
True
False
QUESTION 45
45.If slack time for B,D,E and G are zero, the critical path for this project is B-D-E-G
True
False
Problem 4: (5) E (7) Start B (6) D (3) (8) C (4) F (7) Answer questions 41, 42,43,44 and 45 based on Problem 4Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock