Question: 41. For the above project network (times is given in weeks), if EF for activity C is week 4 and EF for activity F is

41. For the above project network (times is given

41. For the above project network (times is given in weeks), if EF for activity C is week 4 and EF for activity F is week 11

True

False

42.For the above project network, if LS for activity G is week 16, LS for activity F is week 9

True

False

QUESTION 43

43.For the above project network if LS for activity E is week 9, LS for activity D is week 4

True

False

QUESTION 44

44. If LF=9 and LS=5 for activity C, we can say its slack is 4 and is a non-critical activity

True

False

QUESTION 45

45.If slack time for B,D,E and G are zero, the critical path for this project is B-D-E-G

True

False

Problem 4: (5) E (7) Start B (6) D (3) (8) C (4) F (7) Answer questions 41, 42,43,44 and 45 based on Problem 4

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!