Question: 41.For the above project network (times is given in weeks), if EF for activity C is week 4 and EF for activity F is week

  1. 41.For the above project network (times is given in weeks), if EF for activity C is week 4 and EF for activity F is week 7

    True

    False

42.For the above project network, if LS for activity G is week 16, LF for activity F is week 16

  1. True

    FalseContinue

  2. 43.For the above project network if LS for activity E is week 9, LS for activity D is week 4

    True

    False

  3. 44.If LF=9 and LS=5 for activity C, we can say its slack is 4 and is a non-critical activity

    True

    False

  4. 45.If slack time for B,D,E and G are zero, the critical path for this project is B-D-E-G

    True

    False

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!