Question: 5- Based on information provided in the above table what is the peak resource demand for R1 using time constraint scheduleing (the duration must not
5-

Based on information provided in the above table what is the peak resource demand for R1 using time constraint scheduleing (the duration must not change)?
A) 7
B) 2
C) 6
D) 4
Step by Step Solution
There are 3 Steps involved in it