Question: In a CPM network, the critical path includes five activities. Their durations are tabulated next. table [ [ , Duration ( Days ) ]

In a CPM network, the critical path includes five activities. Their durations are tabulated next.
\table[[,Duration (Days)],[Activity,Optimistic (To),Most Likely (Tm),Pessimistic (Tp)],[A,2,4,7],[B,5,8,14],[C,4,6,8],[D,2,2,2],[E,7,10,21]]
Compute the following nine values:
The probability that the project will finish by the end of day 32
The probability that the project will finish by the end of day 34
The probability that the project will finish before day 30
The probability that the project will finish on day 32