Question: 52. Consider the project digraph shown in Fig. 8-40. (a) Schedule the project with N=3 processors using the critical-path algorithm. Show the timeline, and give

52. Consider the project digraph shown in Fig.

52. Consider the project digraph shown in Fig. 8-40. (a) Schedule the project with N=3 processors using the critical-path algorithm. Show the timeline, and give the project finishing time. (b) Explain why the schedule obtained in (a) is optimal. A(8) D(12) F(1) B(5) ( START(0) O END(0) C(9) E(6) G(2) FIGURE 8-40