Question: A small software development project has eight major activities. The times are estimated and provided in the table 1 - 2 below. All times are

A small software development project has eight major activities. The times are estimated and provided in the table 1-2 below. All times are in weeks. Answer Question # 6 to 10:
\table[[Activity,Optimistic,Most,Pessimistic,Immediate],[,Time,Likely Time,Time,Predecessor(s)],[A,3,4,5,--],[B,5,7,9,--],[C,2,3,10,A],[D,2,5,8,B],[E,1,7,7,B],[F,3,5,7,C, D],[G,7,8,9,D, E],[H,2,6,10,F]]