Question: 6.2) Analyze the following activity time estimates table and complete the subsequent questions. Most Task ID Activity Predecessor Optimistic Pessimistic Estimated Time likely 1
6.2) Analyze the following activity time estimates table and complete the subsequent questions. Most Task ID Activity Predecessor Optimistic Pessimistic Estimated Time likely 1 Build house 0 Dig 2 foundation 1 7 9 10 3 Build walls 2 15 18 33 20 4 Build roof 3 10 5 Install faucets 1 2 6 Install fixtures 5 4 7 6 3 Install carpets Finished 8 house 0 0 6.2.1) Create the network diagram for this activity. 6.2.2) Calculate the pessimistic time to dig the foundation. 6.2.3) Calculate the critical time. (6)
Step by Step Solution
3.51 Rating (161 Votes )
There are 3 Steps involved in it
Answer 621 10 a 10 O 10 30 40 6 4 10 3 30 1 ... View full answer