Question: ( 7 0 points ) For each network below ( Project ( a ) and Project ( b ) ) , you should determine by

(70 points) For each network below (Project (a) and Project (b)), you should determine by hand:
(1) the earliest time for each event (node)
(2) the latest time for each event (node)
(3) the slack time for each activity (arc)
(4) the critical activities (arcs)
(5) all critical paths in the network from node 1 to node 7
(6) the duration of the project
For each project, also verify your results using TORA (include a screenshot of your TORA results for each network).
Project (a)
Project (b)
 (70 points) For each network below (Project (a) and Project (b)),