Question: Develop a network diagram and compute Early Start ( ES ) , Early Finish ( EF ) , Late Start ( LS ) , Late
Develop a network diagram and compute Early Start ES Early Finish EF Late Start LS Late
Finish LF Total Float TF and Free Float FF for each activity. points
What is the overall project duration? points
Determine the critical paths in the project points
Utilize Microsoft Excel to generate a Gantt chart for the project manager, referencing the
network. The project initiation is scheduled for February and assumes a day
workweek. Account for a holiday on February points
Generate a tabular report for the project manager on the Excel sheet, derived from the Gantt
chart you constructed. points