Question: Given the project within the table below, calculate the following: a. The critical path b. The minimum project duration c. What is the critical path

 Given the project within the table below, calculate the following: a.

Given the project within the table below, calculate the following: a. The critical path b. The minimum project duration c. What is the critical path of this network? List the ES EF LS LF and the amount of slack for each activity

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To solve the problem we need to 1 Determine the critical path 2 Calculate the minimum project durati... View full answer