Question: 7 Task Optimistic Most Likely A 2 7 B 8 14 6 15 D 8 11 E 6 14 F 9 G S 7 7

7 Task Optimistic Most Likely A 2 7 B 8 14 6 15 D

7 Task Optimistic Most Likely A 2 7 B 8 14 6 15 D 8 11 E 6 14 F 9 G S 7 7 8 3 9 15 17 K 7 19 L 8 11 M 2 Pessimistic 12 26 18 20 22 17 15 9 21 25 37 20 3 A G 12 8 1 10 18 Start B 15 E 14 M 2 K 20 C 14 E 10 L 12 8 1. What is the critical path for this project? 2. What is the slack on each activity? 3. What is the probability of completing the critical path in 60 weeks? 4. What completion time would give you a 99% confidence of completing the critical path on-time

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!