Question: You are creating a customer database for the Hillsboro Hops minor league baseball team. Given the Iinformation below, complete the forward and backward pass,
You are creating a customer database for the Hillsboro Hops minor league baseball team. Given the Iinformation below, complete the forward and backward pass, compute activity slack, and identify the critical path. Time ID Description Predecessor (days) A Systems Subsystem A design Subsystem B design Subsystem C design Program A Program B Program C Subsystem A Subsystem B Subsystem C Integration Integration test None 4 B A A D A 3 B 4 F G D 4 H E 4 I F 4 K , I, ) 4 L K The project will take The early start on Activity D is The late start on Activity E is The late finish on Activity I is days. days. days. days. Calculate the free slack and total slack for all noncritical activities (Click to select) How sensitive is the network schedule? (Click to select)
Step by Step Solution
3.43 Rating (169 Votes )
There are 3 Steps involved in it
Forward Pass ActivityEarly StartEarly FinishDuration days A044 B484 C8113 D891 E9134 F11154 ... View full answer
Get step-by-step solutions from verified subject matter experts