Question: You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. Draw a project network given the information below. Complete the

You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. Draw a project network given the information below. Complete the forward and backward pass, compute activity slack, and identify the critical path.

How long will this project take? How sensitive is the network schedule? Calculate the free slack and total slack for all noncritical activities.

ID Description Predecessor Time (days) A Systems design None Subsystem A design A 1 C Subsystem B design 2 Subsystem C d

ID Description Predecessor Time (days) A Systems design None Subsystem A design A 1 C Subsystem B design 2 Subsystem C design A Program A B 2 Program B 10 G Program C D 3 Subsystem A test Subsystem B test 1 Subsystem C test G K Integration , I, J 3 Integration test K

Step by Step Solution

3.23 Rating (161 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Early start late start early finish late finish and slack are shown on the ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

1379-B-M-L-P-M(2672).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!