Question: 8. Given the information below, create the project schedule network. Then, using the two-pass method, calculate and show the early and late starts and float

8. Given the information below, create the

8. Given the information below, create the project schedule network. Then, using the two-pass method, calculate and show the early and late starts and float for each activity and the critical path. Show the schedule on a Gantt chart show- ing critical and noncritical activities and float. IMMEDIATE PREDECESSOR ACTIVITY DAYS A B 2 A 4 A D 7 A E 3 B F 6 B, C G 8 D, E, F