Question: Given the information below, create the project schedule network. Then, using the two-pass method, calculate and show the early and late starts and float for
Given the information below, create the project schedule network. Then, using the two-pass method, calculate and show the early and late starts and float for each activity and the critical path. Show the schedule on a Gantt chart showing critical and non-critical activities and float.

Activity A B C D E F G Days 5 2 4 7 3 6 8 Immediate Predecessor A A A B B, C D, E, F