Question: 9.2. Construct a Gantt chart for the project described by the following set of activities, and indicate the project completion time and the available slack

9.2. Construct a Gantt chart for the project described by the following set of activities, and indicate the project completion time and the available slack for each activity:

Activity Activity Predecessor Time (Weeks)

1 3

2 7

3 1 2

4 2 5

5 2 6

6 4 1

7 5 4