Question: 9.2. Construct a Gantt chart for the project described by the following set of activities, and indicate the project completion time and the available slack
9.2. Construct a Gantt chart for the project described by the following set of activities, and indicate the project completion time and the available slack for each activity:
Activity Activity Predecessor Time (Weeks)
1 3
2 7
3 1 2
4 2 5
5 2 6
6 4 1
7 5 4