Question: Construct a Gantt chart for the project described by the following set of activities, and indicate the project completion time and the available slack for
Construct a Gantt chart for the project described by the following set of activities, and indicate the project completion time and the available slack for each activity:
| ACTIVITY | ACTIVITY PREDECESSOR | TIME (WEEKS) |
| 1 | 3 | |
| 2 | 7 | |
| 3 | 1 | 2 |
| 4 | 2 | 5 |
| 5 | 2 | 6 |
| 6 | 4 | 1 |
| 7 | 5 | 4 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
