Question: 9.2 Construct a Gantt chart for the project described by the following set of activities, and indicate the project completion time and the available slack
9.2Construct a Gantt chart for the project described by the following set of activities, and indicate the project completion time and the available slack for each activity:
construct a gantt chart that shows the timeline from start to end. meaning create an a-o-n network diagram using the information given in the Table. next, create a table of activity versus slack (wks) and state which specific activities are on the critical path.
| ACTIVITY | ACTIVITY PREDECESSOR | TIME (WEEKS) |
| 1 | - | 4 |
| 2 | - | 7 |
| 3 | 1 | 8 |
| 4 | 1 | 3 |
| 5 | 2 | 9 |
| 6 | 3 | 5 |
| 7 | 3 | 2 |
| 8 | 4,5,6 | 6 |
| 9 | 2 | 5 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
