Question: A. (15 Marks) You have evaluated your project and have developed the following earned value table from your analysis. Tasks EV PV AC CY CPI

A. (15 Marks) You have evaluated your project and
A. (15 Marks) You have evaluated your project and have developed the following earned value table from your analysis. Tasks EV PV AC CY CPI SV SPI Task A $10,000 $10,000 $11,000 Task B 12,000 11,000 13,000 TaskC 9,000 8,000 8,500 1. Determine the project status by calculating CV, CPI, SV, and SPI for each task and for the project overall 2. What is the analysis of how the project is doing from these indicators