Question: A 2 3 5 none B 2.3 4 5 A C 5 8 8 A D 3 5 7 B, C E 4 7 13

A

2 3 5 none

B

2.3 4 5 A

C

5 8 8 A

D

3 5 7 B, C

E

4 7 13 B, C

F

2 5 9 D

G

4 5 6 E

H

6 6 9 F

I

4 9 12 G

J

2 3 3 H, I

The critical path is A-C-E-G-I-J.

Activity

A

B

C

D

E

F

G

H

I

J

Variance

0.25 0.20 0.25 0.44 2.25 1.36 0.11 0.25 1.78 0.03

(a) Calculate the probability that the project will be completed in 33 weeks. (Round your answer to 4 decimal places, e.g. 1.7945.)

P(project 33) = enter a probability

(b) Calculate the probability that the project will be completed in 37 weeks. (Round your answer to 4 decimal places, e.g. 1.7945.)

P(project 37) = enter a probability

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!