Question: A 2 3 5 none B 2.3 4 5 A C 5 8 8 A D 3 5 7 B, C E 4 7 13
| A | 2 | 3 | 5 | none | ||||
|---|---|---|---|---|---|---|---|---|
| B | 2.3 | 4 | 5 | A | ||||
| C | 5 | 8 | 8 | A | ||||
| D | 3 | 5 | 7 | B, C | ||||
| E | 4 | 7 | 13 | B, C | ||||
| F | 2 | 5 | 9 | D | ||||
| G | 4 | 5 | 6 | E | ||||
| H | 6 | 6 | 9 | F | ||||
| I | 4 | 9 | 12 | G | ||||
| J | 2 | 3 | 3 | H, I |
The critical path is A-C-E-G-I-J.
| Activity | A | B | C | D | E | F | G | H | I | J |
|---|---|---|---|---|---|---|---|---|---|---|
| Variance | 0.25 | 0.20 | 0.25 | 0.44 | 2.25 | 1.36 | 0.11 | 0.25 | 1.78 | 0.03 |
(a) Calculate the probability that the project will be completed in 33 weeks. (Round your answer to 4 decimal places, e.g. 1.7945.)
P(project 33) = enter a probability
(b) Calculate the probability that the project will be completed in 37 weeks. (Round your answer to 4 decimal places, e.g. 1.7945.)
P(project 37) = enter a probability