Question: Using the following project information Activity Optimistic Time Estimate(weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) A 2 3 5 none

Using the following project information

Activity Optimistic Time Estimate(weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s)
A 2 3 5 none
B 2.5 4 5 A
C 5 7 8 A
D 3 5 7 B, C
E 4 6 13 B, C
F 2 5 7 D
G 4 5 6 E
H 6 7 9 F
I 4 8 11 G
J 2 3 3 H, I

The critical path is A-C-E-G-I-J.

Activity A B C D E F G H I J
Variance 0.25 0.17 0.25 0.44 2.25 0.69 0.11 0.25 1.36 0.03

(a) Calculate the probability that the project will be completed in 31 weeks. (Round your answer to 4 decimal places, e.g. 1.7945.)

P(project 31) = enter a probability

(b) Calculate the probability that the project will be completed in 34 weeks. (Round your answer to 4 decimal places, e.g. 1.7945.)

P(project 34) = enter a probability

eTextbook and Media

Save for Later

Attempts: 0 of 3 used

Submit Answer

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!