Question: Using the following project information Activity Optimistic Time Estimate(weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) A 2 3 5 none

Using the following project information

Activity

Optimistic Time Estimate(weeks)

Most Likely Time Estimates (weeks)

Pessimistic Time Estimates (weeks)

Immediate Predecessor(s)

A

2 3 5 none

B

2.6 4 5 A

C

5 7 8 A

D

3 5 8 B, C

E

4 6 13 B, C

F

2 5 8 D

G

4 5 7 E

H

6 6 9 F

I

4 8 11 G

J

2 3 3 H, I

The critical path is A-C-E-G-I-J.

Activity

A

B

C

D

E

F

G

H

I

J

Variance

0.25 0.16 0.25 0.69 2.25 1.00 0.25 0.25 1.36 0.03

(a) Calculate the probability that the project will be completed in 31 weeks. (Round your answer to 4 decimal places, e.g. 1.7945.)

P(project 31)=

(b) Calculate the probability that the project will be completed in 35 weeks. (Round your answer to 4 decimal places, e.g. 1.7945.)

P(project 35) =

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!