Question: (a) A civil engineering project is described by the data given in Table Q1. Develop a Gantt chart for the project and discuss risks associated

(a) A civil engineering project is described by

(a) A civil engineering project is described by the data given in Table Q1. Develop a Gantt chart for the project and discuss risks associated with critical path activities. [10 marks] Table Q1 Activity Predecessor Duration A 1 B A 3 B 4 D B 2 E . 6 F C D 5 G F 3 H F G 3 1 E 13 J I, H 1