Question: a . A factory is building a robot using an assembly line that consists of the following tasks with their respective durations ( in hours

a. A factory is building a robot using an assembly line that consists of the following tasks with their respective
durations (in hours):
Task A: 2 hours
Task B: 4 hours (depends on Task A)
Task C: 3 hours (depends on Task A)
Task D: 5 hours (depends on Tasks B and C)
Task E: 2 hours (depends on Task D)
i. Draw the project network diagram and identify the critical path .
ii. Calculate the total duration to complete the project.
b. Consider the field of embodied Al, where agents interact with their environments to perform tasks. Discuss
the following aspects:
i. What is an embodied Al?
ii. How does embodied Al differ from traauuna Al approaches?
iii. Briefly describe some major challenges in the design of embodied Al systems. How do you propose to
solve them?
iv. Briefly discuss the role of knowledge representation and planning in the design of embodied Al systems
through a simple example.
c. Knowledge Representation:
i. Compare between propositional logic and predicate logic - as methods of knowledge representation -
through a simple example.
ii. Use production rules to design a simple expert system that is capable of predicting heart diseases to
assist a healthcare professional.
 a. A factory is building a robot using an assembly line

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!