Question: a. An activity has these time estimates: optimistic = 6, most likely = 10, and pessimistic = 16. write down Its expected time. (Give your
a. An activity has these time estimates: optimistic = 6, most likely = 10, and pessimistic = 16. write down Its expected time. (Give your answer to two decimal places)